Proposed Phases

Updated: 7 days ago


We now have the proposed project phasing from B&K. This may change as the project progresses but the headline timeline for various aspects of the project is below. We have spent considerable time working with B&K to ensure that throughout the whole project the school remains fully open and a safe space for everyone to be working. As with any project like this there will be some disruption but the phasing keeps this to the absolute minimum.

July 2021 Contractor starts on site.

05/07/2021 – 20/08/2021 Construct temporary road to side of field and move PE shed. This includes 24 additional car park spaces.

05/07/2021 - 19/07/2021 Move out of the Sports block and 500/600 rooms

19/07/2021 – 03/12/2021 Make all the trenches for the new Gas, Electric, Water and fibre cable runs and drainage.

19/07/2021 - 13/09/2021 Asbestos removal from Sports Hall block

23/08/2021 - 31/03/2022 Sports Hall block is fully refurbished

04/10/2021 – 17/12/2021 Make new 56 space car park to the front of the school buildings

06/12/2021 – 25/11/2022 Building A on the rear tennis courts is built

04/01/2022 – 09/12/2022 Building B on the front car park is built.

23/12/2022 – 09/01/2023 Move into both new buildings and use them from 09/01/2023.

23/01/2023 – 10/08/2023 Old science block is demolished

06/02/2023 – 10/05/2023 Asbestos removal from old Main building – all staff and lesson no longer in there.

08/05/2023 – 03/05/2024 Main building fully refurbished.

20/05/2024 - 01/06/2024 Move back into Main building

03/06/2024 – 19/07/2024 road removed from field.

22/07/2024 project completed.